Permits & Costs · San Diego
How Much Are Building Permit Fees in San Diego for a Remodel or New Home? (2026)
The City of San Diego calculates plan-check fees from a base charge plus a per-square-foot rate that changes by project type. Here is exactly how that math works for a remodel and for new construction, using the city’s own fee schedule.
Updated September 2026
Read time 9 min
Key takeaways
- The City of San Diego’s Tenant Improvement/Remodel plan-check fee is a $2,532.77 base charge that covers the first 2,000 square feet of remodeled space, per Information Bulletin 501 (effective August 2026).
- A new single-family home under 3,000 square feet pays an $8,085.26 base plan-check fee before any square-foot increment applies.
- Above those size thresholds, the city adds $1.33 per square foot for a remodel and $4.10 per square foot for new construction.
- Electrical, plumbing and mechanical work is billed under a separate MEP permit, starting with a $12.16 mapping fee per Information Bulletin 103.
- Plan-check and issuance fees are a small slice of total project cost — not a substitute for a full construction budget.
- Fee schedules are updated by the city periodically, so confirm current rates before finalizing a budget.
In this guide
- What “building permit fees” actually cover
- How the city calculates your plan-check fee
- Example: a kitchen-and-bath remodel
- Example: a new single-family home
- MEP permits: the fees added on top
- Other city and state fees to budget for
- When design work triggers extra requirements
- Permit fees vs. total project cost
What “building permit fees” actually cover
“Permit fees” is really a stack of separate charges, not one number. The City of San Diego’s Development Services Department collects a submittal fee when you apply, a plan-check fee while staff reviews your drawings, and a set of issuance fees when the permit is finally released. Trade permits for electrical, plumbing and mechanical work are billed separately from the building plan-check fee. None of this includes the cost of design, engineering, materials or labor — it is strictly what the city charges to review and inspect the work.
Every figure below comes from two current city publications: Information Bulletin 501, Fee Schedule for Construction Permits-Structures (effective August 2026), and Information Bulletin 103, Fee Schedule for Mechanical, Electrical, Plumbing/Gas Permits (effective May 2026). Both are linked in the sources section below so you can check the current numbers before you budget.
How the city calculates your plan-check fee
San Diego’s plan-check fee is a base charge that already covers a set amount of square footage, plus a per-square-foot rate once your project crosses that threshold. The formula is different for a remodel than for new construction, which is why an addition and a ground-up build are not priced the same way.
| Project type | Base plan-check fee | Square feet included in base | Rate above that |
|---|---|---|---|
| Tenant Improvement / Remodel | $2,532.77 | 2,000 sq ft | $1.33 / sq ft |
| Single Dwelling Unit / Duplex (new construction) | $8,085.26 | 3,000 sq ft | $4.10 / sq ft |
| New Commercial | $4,566.31 | 3,000 sq ft | $1.57 / sq ft |
Notice that the remodel base fee stays flat for anything up to 2,000 square feet. A small kitchen or bathroom project almost never triggers the per-square-foot increment at all — the increment mostly matters on a large whole-home remodel or an addition that pushes the remodeled area past that line.
Example: a kitchen-and-bath remodel
Say you are remodeling a kitchen and two bathrooms, and the remodeled floor area totals under 2,000 square feet. Under the Tenant Improvement/Remodel formula in Table 1, that project pays the flat $2,532.77 plan-check fee — the per-square-foot rate does not apply because the project stays under the 2,000-square-foot threshold built into the base charge.
If the remodeled area runs larger — say a whole-home remodel touching 2,600 square feet — the math adds the increment for the extra 600 square feet (600 sq ft × $1.33 per sq ft = $798 increment), for a plan-check total of roughly $3,331 before any MEP permits are added. (See the MEP section below — a kitchen or bathroom remodel almost always needs those too.) For permit-specific guidance on a kitchen project specifically, see our kitchen remodel permit guide and bathroom remodel permit guide.
Example: a new single-family home
New construction uses a different base and a different threshold. A new single-family home under 3,000 square feet pays the flat $8,085.26 base plan-check fee from Table 1. Above that size, the city adds $4.10 for every additional square foot. A 3,800-square-foot custom home, for example, would add 800 square feet worth of increment (800 sq ft × $4.10 per sq ft = $3,280 increment) on top of the base, for a plan-check total near $11,365. That figure is the plan-check fee alone; it does not include issuance fees, MEP permits, or any impact fees discussed below.
These examples use round, hypothetical square footages purely to show how the formula works. Your project’s actual fee depends on the exact plan-checked area the city assigns to your drawings.
MEP permits: the fees added on top
Electrical, plumbing and mechanical work is not included in the building plan-check fee — it is billed as a separate MEP (mechanical/electrical/plumbing) permit. Every MEP permit starts with a small mapping fee, then adds a charge per circuit, fixture or piece of equipment.
| Fee item | Cost |
|---|---|
| Mapping fee (applies once per MEP permit) | $12.16 |
| Electrical, first 5 circuits (15–45 amp) | $176.57 |
| Electrical, each additional circuit | $52.39 |
| Plumbing fixture (per fixture) | $87.68–$353.13 |
| Mechanical equipment (per unit) | $87.68–$529.71 |
A kitchen remodel that relocates a sink, adds circuits for new appliances and installs a range hood will typically cross several of these line items at once. The bulletin lists the full fixture-by-fixture and equipment-by-equipment schedule; the rows above are the ones homeowners ask about most.
Other city and state fees to budget for
Beyond the plan-check and MEP fees, a handful of smaller charges are collected when the permit is issued. These do not depend on project type the way the plan-check fee does — they are based on your project’s construction valuation or the age of the structure.
- Lead Hazard Prevention Fee — $58.00 flat, applies only to structures built before 1978.
- State Seismic Fee — $0.13 per $1,000 of construction valuation for single-family homes and duplexes.
- State Building Standards Fee — $4.00 per $100,000 of construction valuation, with a $1.00 minimum.
- Mapping fee — $12.16, charged once on the building permit in addition to any MEP mapping fees.
Depending on your project, the city may also collect water and sewer capacity charges, school district fees, or one of several development impact fees. Those are calculated case by case and are not fixed dollar amounts in the published bulletins, so Development Services staff should confirm them for your specific address and scope before you finalize a budget.
When design work triggers extra requirements
Some projects need an energy compliance report — a HERS rating — before the city will issue a permit. Per Information Bulletin 103, that requirement applies to new residential construction, major HVAC replacements, additions larger than 1,000 square feet, and any project installing more than 40 feet of new ductwork. If your remodel or addition falls into one of those categories, budget time in the design and engineering phase for that report — it is a separate scope item from the plan-check fee itself, and it needs to be resolved before drawings go to the city for review.
Every dollar figure in this guide is a city plan-check or issuance fee pulled directly from the current published bulletins — not a project cost, not a design or construction estimate, and not an Eco Home Builders quote. Cities revise these schedules periodically, and other agencies (water, sewer, school district) can add fees not shown here. Confirm current amounts with San Diego Development Services before you set a project budget.
Permit fees vs. total project cost
It’s worth separating the permit fee from the price of the project itself. Even the largest plan-check fee in this guide is a small fraction of what a remodel typically costs to design and build. For scale, the table below shows average total job costs from an independent industry report — not permit fees, and not San Diego-specific numbers, but a useful reference point for how far a permit fee goes relative to the overall project.
| Project type | Average job cost | Average resale value |
|---|---|---|
| Minor kitchen remodel | $29,728 | $38,384 |
| Major kitchen remodel | $86,480 | $49,467 |
| Bathroom remodel | $27,710 | $25,217 |
Against those job-cost figures, even a fully-loaded plan-check and MEP fee package for a mid-size remodel typically lands in the low thousands — real money, but not the number that should drive your go/no-go decision on a project. For a broader look at how to scope a project before it reaches the permit counter, see our guide on choosing between a full and partial remodel.
How much is the plan-check fee for a kitchen or bathroom remodel in San Diego?
Per Information Bulletin 501 (effective August 2026), a remodel under 2,000 square feet of remodeled area pays the flat Tenant Improvement/Remodel base fee of $2,532.77. Larger remodels add $1.33 per square foot above that threshold. This is the plan-check fee only — electrical, plumbing and mechanical work is billed separately.
How much is the plan-check fee for a new single-family home?
A new single-family home or duplex under 3,000 square feet pays an $8,085.26 base plan-check fee, per Information Bulletin 501. Above 3,000 square feet, the city adds $4.10 per additional square foot.
Do these fees include electrical, plumbing and mechanical permits?
No. MEP (mechanical/electrical/plumbing) work is permitted separately from the building plan-check fee. Per Information Bulletin 103, each MEP permit starts with a $12.16 mapping fee, then adds charges per circuit, fixture or piece of equipment.
Are permit fees the same as my total remodeling or construction budget?
No. Permit fees cover the city’s plan review and inspection only. They do not include design, engineering, materials, labor or contractor overhead. Independent industry data (the 2025 Cost vs. Value Report) puts the average Pacific-region job cost for a minor kitchen remodel at $29,728 — permit fees are a small fraction of that total.
What other fees might be added on top of the plan-check fee?
Depending on the project, you may also see a State Seismic Fee ($0.13 per $1,000 of construction valuation), a State Building Standards Fee ($4.00 per $100,000 of valuation, $1.00 minimum), a Lead Hazard Prevention Fee ($58.00 on structures built before 1978), and case-by-case charges such as water/sewer capacity fees or school district fees. Development Services can confirm which apply to your address.
Does a remodel or addition need a HERS rating?
Per Information Bulletin 103, a HERS energy compliance rating is required for new residential construction, major HVAC replacements, additions larger than 1,000 square feet, and any project installing more than 40 feet of new ductwork. Smaller remodels that don’t touch HVAC or ductwork at that scale typically don’t trigger it.
Do San Diego’s permit fees change every year?
Yes. The bulletins cited in this guide are dated May 2026 (Information Bulletin 103) and August 2026 (Information Bulletin 501), and the city updates them periodically. Always check the current bulletin before finalizing a project budget.
Ready to build or remodel in San Diego?
Eco Home Builders handles design, engineering and permitting for whole-home remodels, additions and new construction across San Diego and Orange County. Schedule a consultation to get a clear scope and permit path for your project.
Sources
- City of San Diego, Information Bulletin 501 — Fee Schedule for Construction Permits-Structures (effective August 2026)
- City of San Diego, Information Bulletin 103 — Fee Schedule for Mechanical, Electrical, Plumbing/Gas Permits (effective May 2026)
- 2025 Cost vs. Value Report, Pacific Region — Zonda Media / JLC
- City of San Diego Development Services — Permits
Cost figures in this article are third-party benchmarks and published city fee schedules, not Eco Home Builders quotes. Actual permit fees and project costs vary by scope, address and current city rate schedules.